W.P.(C)/5590/2015 of SHAMNAD BASHEER Vs UNION OF INDIA & ORS
Parties
- SHAMNAD BASHEER (PETITIONER)
- UNION OF INDIA & ORS (RESPONDENT)
Cites (1)
Full text
solid underline = linked page · dashed underline = case is in our corpus, page not published yet · dotted red = recognized reference, not in our corpus
*IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 5590/2015 & CM No.10090/2018
Date of decision : 23[rd] April, 2018
SHAMNAD BASHEER ..... Petitioner Through : Mr. Abhimanyu Bhandari and Mr. N. Sai Vinod, Advs. versus UNION OF INDIA & ORS ..... Respondents Through : Mr. Amit Mahajan, CGSC for R-1/UOI Mr. Rajiv Nayyar, Sr. Adv.with Mrs. Saya Chaudhary, Mr. Ashutosh Kumar, Mr. Prateek Sehrawat, Mr. A. Joyaraj and Mr. Devanshu Khanna, Advs. for Intervenor-Ericsson Mr. Rajiv Kr. Choudhry, Adv. for Intervenor-TEMA Ms. Pritha Srikumar Iyer and Mr. Nishanth Kadur, Advs. for R-4
CORAM:
HON'BLE THE ACTING CHIEF JUSTICE HON'BLE MR. JUSTICE C.HARI SHANKAR
JUDGMENT (ORAL)
GITA MITTAL, ACTING CHIEF JUSTICE
1.This writ petition is concerned with issues relating to the working of patents under the Patents Act, 1970. It appears that concerned with
W.P.(C)No5590/2015 Page 1 of 4
the several issues relating to Section 146 of the Patents Act, 1970 (as amended) read with Rule 131 of Patents Rules, 2003; Form 27 prescribed therein and the implementation of the provisions provided under Section 122, the office of the Controller General of Patents, Designs and Trademarks has initiated an exercise of examination of these provisions from the perspective as to whether changes/amendments thereto need to be effected.
2.In this regard, stakeholder consultation meeting was scheduled to be held on 21[st] March, 2018. We are informed that pursuant thereto, stakeholder consultation has actually been held at Delhi on 6[th] April, 2018.
3.By our order dated 15[th] March, 2018, we had directed the respondent no.1 to place before this court reasonable timeline within which the consultation would be completed, suggestions received, examined and such amendments as may be deemed necessary, effected to the Patents Act, 1970 and Rules thereunder. Pursuant to our directions, respondent no.1 has filed an affidavit dated 20[th] April, 2018 by Dr. Suman Shrey Singh, Deputy Controller of Patents & Designs in the Patents Office, Delhi, who is also personally present in court.
4.We have been taken through this affidavit by Mr. Amit Mahajan, learned Standing Counsel for the Central Government. Alongwith this affidavit, the respondents have placed the following timelines for consideration of the matter and to effect such changes as may be necessary in the provisions of the Patents Act and the Rules :
W.P.(C)No5590/2015 Page 2 of 4
“3.Accordingly, the following sequential timelines to complete all the actions to be taken by the office of CGPDTM/Ministry related to this matter are submitted.
5.As noted above, the steps till serial no. 3 i.e. the stakeholder consultation meeting held on 6[th] April, 2018 stand completed.
6.We accept the timelines suggested by the respondent no.1 who shall remain bound by the same. Every effort shall be made to ensure that there is no deviation and the matter is treated in right earnest and given the seriousness which it deserves to be accorded to it.
7.The respondents shall place report before this court upon completion of the aforesaid noticed exercise.
8.In view of the above, this writ petition and application which sought the strict implementation of the law need not detain this court any further and are hereby disposed of.
ACTING CHIEF JUSTICE
APRIL 23, 2018/kr
C.HARI SHANKAR, J
W.P.(C)No5590/2015 Page 4 of 4