AO/1063/1995 of TEHRI HYDRO DEVELOPMENT CORPORATION LTD. Vs KARAM CHAND THAPAR AND BROS. LTD. TICIL
Parties
- Tehri Hydro Development Corporation Ltd (PETITIONER)
- Karam Chand Thapar and Bros. (Coal Sales) Ltd. Tehri, District Tehri Garhwal and another (RESPONDENT)
Cites (3 resolved of 12 detected)
- OIL & NATURAL GAS CORPORATION LTD. versus SAW PIPES LTD. (2003)
- AIR 1989 SC 890 (1989) FOLLOWED
- AIR 1987 SC 23 (1987) CONSIDERED
Statutes cited (5)
Full text
solid underline = linked page · dashed underline = case is in our corpus, page not published yet · dotted red = recognized reference, not in our corpus
(Court’s order whether the case is or not approved for reporting)
(Chapter VIII Rule 32 (2) (b)
Description of the case.
A.O. No. 1519 of 2001
Tehri Hydro Development Corporation Ltd.
Karam Chand Thapar and Bros. (Coal Sales) Ltd. Tehri, District Tehri Garhwal and another
Approved for reporting.
Not approved for reporting Date of decision 23.12.2004
Initial of Judge
A.O. No. 1519 of 2001
Old No. 1063 of 1995
Tehri Hydro Development Corporation
Ltd. …………Appellant
Versus
1. Karam Chand Thapar and Bros. (Coal Sales)
Ltd; Tehri, District Tehri Garhwal and another
2. State of U.P. ……………..Respondents.
Sri U.K. Uniyal Sr. Advocate assisted by Sri Sobhit Saharia, Advocate. Sri V.K. Kohli, Sr. Advocate assisted by Sri I.P. Kholi, Advocate.
Dated: December 23,2004
Hon’ble Rajesh Tandon, J.
Heard the learned counsel for the partiers.
Present appeal has been filed against the judgment and
order dated 4.8.1995 passed by the District Judge, Tehri Garhwal, thereby rejecting the petition of the appellant under section 30 and 33 of the Arbitration Act for setting aside the award.
Briefly stated, as agreement was entered between the
appellant and respondent no.1 on 28.4.1978 for manufacturing Chain Link Fabric of approximate 50mm mesh woven form 9 SWG steel wires. The respondent no.1 did not use 9 SWG steel wires and used 10 SE Steel wires, which is inferior in quality for
Chain Link Fabric of approximate 50mm mesh woven form 9
manufacturing the chain link fabric. The appellant accordingly
reduced the amount to Rs.55/- PER Sq.M. whereas the
respondent no. 1 claimed rate of Rs. 71/- per Sq. M., which was refused by the appellant. This raised dispute, which was referred to arbitration.
refused by the appellant. This raised dispute, which was
The arbitrators gave an award on 5.31994 allowing the
claim of respondent no.1 and fixed the rate of Rs.65/- per sq. m.
The arbitrators accordingly held that Rs.1,92,347.28 was
payable to the claimant respondent no.1. They further allowed
payment of interest @ 12% per annum of the aforesaid amount
from 23.11.1987 to 5.3.1994 and further interest @ 6% on the
principal amount from the date of award to the date of decree.
Respondent no.1 has filed objections in proceedings under
has submitted that as per directions of the contract chain link
fabric was to be made out 9 SWG wire as per directions of the
Engineer-in charge. The contractor made fabric out of 10 SWG
wire, which is lighter and cheaper requiring less material and
labour and deduction at the rate of Rs.5/- per Sq. m. was
rightfully made which was conveyed to the contractor vide letter
dated 12.9.1987. The appellant has further submitted that the
rate of Rs.55/- per sq.m. payable against this item of work had
been earlier conveyed to the contractor. Contractor received
various payments. The contractor received payment without
any protest. It is also submitted that the award suffers from
factual and legal infirmities.
Respondent Karam Chand Thapar and Brothers filed
objections traversing objections of the appellant. It has been
submitted that the objections are time barred and the award
cannot be challenged on the alleged grounds. It is also
submitted that incorrect facts have been mentioned from the
said of objections.
On the pleadings of the parties, the reference Court has
framed the following issues:
1.Whether arbitrators misconducted themselves in making the award? making the award?
2.Relief, if any?
The District Judge, Tehri Garhwal has recorded finding
that Tehri Hydro Development Corporation was agreeable to
the rate of Rs.60/- at the time of the award. The contractor was
claiming Rs. 70/- and the arbitrator in the peculiar facts truck
the golden mean of Rs. 65/-. The District Judge has held that
the arbitrators did not misconduct themselves in rendering the
the Arbitration Act, vide impugned order dated 4.8.1995. I do
not find any illegality or infirmity in the award passed by the
arbitrators and confirmed by the District Judge, Tehri Garhwal.
However, Mr. U.K. Uniyal, Sr. Advocate for the appellant,
has submitted that the arbitrators had awarded interest
pendent lite notwithstanding the prohibition contained in the
contract against the payment of interest on delayed payments.
Clause 1.2.14 of the contact was relied upon in this behalf and
that clause reads as under:
1.2.14NO CLAIM FOR DELAYED PAYMENT DUE TO DISPUTE ETC.
The contractor agrees that no claim for interest or
damages will be entertained or payable by the Government in
respect of any money or balances which may be lying with the
Government owing to any disputes, difference misunderstanding between the parties or in respect of any delay or omission on the part of the Engineer-in-charge in
misunderstanding between the parties or in respect of any
making intermediate or final payments or in any other respect
whatsoever.
The learned counsel for the appellant has urged that this
clause contained an absolute prohibition against the payment of
interest on account of any delay on the part of the appellant in
making interim or final payment or otherwise.
In support of his contention, the learned counsel for the
appellant has relied upon (2003) 5 SCC 705 Oil & Natural Gas
Corporation Ltd. v. Saw Pipes Ltd. In this case the apex Court
has dealt with the grounds on which court can, under Section
34 (2) of he Arbitration and Conciliation Act, 1996 can set
aside the arbitral award. The Facts of this case are not applicable
to the present case.
The learned counsel has also cited (2001) 2 SCC 721,
Executive Engineer, Dhenkanal Minor Irrigation Division vs.
N.C. Budharaj & others. In that case the apex Court as per
majority has held that arbitrator, whether appointed with or
without intervention of Court, has power to grant interest in
respect of per reference period, provided there is no stipulation
or prohibition in the arbitration agreement excluding his
jurisdiction. The Forum of arbitration created by consent of
parties, with or without intervention of Court, being only
substitute for conventional civil court, it is an unavoidable
necessity that parties be deemed to have agreed by implication
that arbitrator would have the power to award interest in the
same way and same manner as court. In the present case the
arbitrators have awarded no interest for pre-reference period
and this citation is also not applicable to the facts of the present
case.
The learned counsel for the appellant has further placed
reliance on the case law (2002) 5 SCC 679 W.B. State
Warehousing Corp. vs. Sushil Kumar Kayan and others. In this
case the apex Court has held that arbitrator’s jurisdiction to be
determined by taking into consideration whether particular
claim can be raised before an arbitrator. An arbitrator exceeds
jurisdiction if he decides an issue, which cannot be raised before
him by virtue of contract or law. However, the facts of this case
are not similar to the facts of the instant case. The learned
counsel for the appellant has further relied upon (2002) 5 SCC
685, Indian National Congress (I) vs. Institute of Social Welfare
and others. In this case also awarding of interest has been
challenged the apex Court has held that considering the dispute
involved and overall circumstances of the case, the award qua
the rate of interest modified from 15% to 6%.
The learned counsel for the respondent has placed
reliance on (1996) 1 SCC 516 Board of Trustees for the Port of
Calcutta vs. Engineer-De-Space-Age. In this case the apex court
has held that any clause in the agreement does not prohibit the
arbitrator from awarding interest pendente lite. Moreover,
arbitrator has jurisdiction to interpret the clause of the contract
to decide whether interest pendente lite could be awarded by
him thereunder. The apex Court has as under:
“(ii) An arbitrator is an alternative form (sic forum) for resolution of disputes arising between the parties. If so, he must have the power to decide all the disputes or differences arising between the parties. If the arbitrator has not power to award interest pendent lite, the party
claiming it would have to approach the court for that
purpose, even though he may have obtained satisfaction in respect of other claims from the arbitrator This would lead to multiplicity of proceedings.
4. We are not dealing with case in regard to award of
interest for the period prior to the reference. We are dealing
with case in regard to award of interest by the arbitrator
post reference. The short question, therefore, is whether in
view of sub-clause (g) of clause 13 of the contract extracted
earlier the arbitrator was prohibited form granting interest
under the contract. Now the term in sub-clause (g) merely
prohibits the Commissioner from entertaining any claim for
interest and does not prohibit the arbitrator from awarding
interest. The opening words “no claim for interest will be
entertained by the Commissioner” clearly establishes that the
intention was to prohibit the Commissioner from granting
interest on account of delayed payment to the contractor.
Clause has to be strictly construed for the simple reason that as
pointed out by the Constitution Bench, ordinarily, person
who has legitimate claim is entitled to payment within
reasonable time and if the payment has been delayed beyond
reasonable time he can legitimately claim to be compensated
for that delay whatever nomenclature one may gives to his
claim in that behalf. If that be so, we would be justified in
placing strict construction on the term of the contract on
which reliance has been placed. Strictly construed the term of
the contract merely prohibits the Commissioner form paying
interest to the contractor for delayed payment but once the
matter goes to arbitration the discretion of the arbitrator is
not, in any manner, stifled by this term of the contract and the
arbitrator would be entitled to consider the question of grant
of interest pendente lite and award interest if he finds the
claim to be justified. We are, therefore, of the opinion that
under the clause of the contract the arbitrator was in no
manner prohibited form awarding interest pendente lite.
5. Looked at from another point, if there was dispute as to
whether under this terms of the contract the arbitrator was
prohibited form awarding interest pendente lite, that was
matter which fell within the jurisdiction of the arbitrator, as
the arbitrator would have to interpret sub-clause (g) of clause
13 of the contract and decide whether that clause prohibits him
from awarding interest pendente lite. In that case it cannot be
said that the arbitrator had wandered outside the contract to
deny to him jurisdiction to decide the question regarding
payment of interest pendente lite. Even if we were to accept the
contention urged by the learned counsel for the appellant
placing reliance on paragraphs 26 and 29 of the Associated
Engineering Co. case[2] we think, that the arbitrator was well
within his jurisdiction in awarding interest pendente lite.
In present case the arbitrators have awarded sum of
Rs. 1,92,347.28 with interest @ 12% per annum form 23.11.1987
to 5.3.1994 and further interest @ 6% on the principal sum of
Rs. 1,92, 347.28 from the date of the award i.e. 5.3.1994 to the
date of the decree. The District Judge, Tehri Garhwal has also
held that the arbitrators did not misconduct themselves in
rendering the award.
Section 7-A, U.P. Amendment in the Arbitration Act, 1940
reads as under:
“7-A. Whether and in so far as an award is for the
payment of money, the arbitrators or umpire may deem
reasonable to be paid on the principal sum awarded, from the
date of the commencement of the arbitration, as defined in sub
section (3) of Section 37, to the date of award, in addition to
any interest awarded on such principal sum for nay period
prior to such commencement, with further interest at such rate
not exceeding six per cent per annum as the arbitrators or
umpire may deem reasonable on such principal sum from the
date of the award to the date of payment or to such earlier
date as the arbitrators or umpire may think fit, in no case
beyond the date of the decree to be passed on the award.”
Thus Section 7-A of the Arbitration Act, clears the
position regarding award of interest by the arbitrator for the
period of pendency of the reference as well as since the date of
the award. However, the rate of interest from the date of the
award to the date of payment shall not exceed six percent.
Lastly learned counsel for the petitioner has submitted
that the rate of interest awarded by the arbitrators is too high
and actually it ought to have been 6% throughout. I am not
convinced with the argument of the learned counsel for the
petitioner. No interference can be made by the appellate Court
in the rate of interest awarded by the arbitrator in view of the
proposition law laid down by the apex Court in (1999) 7 SCC
399 State of J & K vs Dev Dutt Pandit. The apex Court has
observed as under:
“21. In the present case the arbitrator awarded interest at
the rate of 10% per annum which was reduced by the learned
Single Judge to 6% per annum and upheld by the Division
Bench. Under Section 34 of the Code of Civil Procedure interest
at higher rate than 6% can be awarded where the liability in
relation to the sum so adjudged had arisen out of commercial
transaction. There is nothing on the record to show that
interest awarded by the arbitrator at the rate of 10% is in
contravention of Section 34 of the Code of civil Procedure.
That being so we do not think either the learned Single Judge
or the Division Bench were correct in reducing the rate of
interest as granted by the arbitrator. We would, therefore,
restore the award of interest at the rate of 10% per annum as
granted by the arbitrator from the date the arbitrator entered
into reference till realisation of the amount under the award.”
In view of the law laid down by the apex court in M/s
Sudarsan Trading Co. Vs. The Govt. of Kerala and another AIR
1989 SC 890, the award made by the Arbitrator cannot be
interfered. The observations are quoted below:-
“It is not open to the court to probe the mental process of
the arbitrator and speculate, where no reasons are given by
the arbitrator, as to what impelled the arbitrator to arrive at
his conclusion. See the observations of this Court in Hindustan
Steel Works Construction Ltd. Vs. C. Rajasekhar Rao (1987)
4SCC 93. In the instant case the arbitrator has merely sent out
the claims and given the history of the claims and then
awarded certain amount. He has not spoken his mind
indicating why he has done what he has done; he has narrated
only how he came to make the award. In absence of any
reason for making the award, it is not open to the court to
interfere with the award. Furthermore, in any event,
reasonableness of the reasons given by the arbitrator cannot
be challenged. Appraisement of evidence by the arbitrator is
never matter, which court question and considers. If the
parties have selected their own forum, the deciding forum
must be conceded the power of appraisement of the evidence.
The arbitrator is the sole judge of the quality as well as the
quantity of evidence and it will not be for the Court to take
upon itself the task of being judge on the evidence before the
arbitrator. See the observations of this Court in Municipal
Cropn. Of Delhi VS. Jagan Nath Ashok Kumar (1987) SCC
497;(AIR 1987 SC 23(6).”
In view of the law laid down above, no interference can be
made in the rate of interest awarded by the arbitrators and
confirmed by the District Judge.
Consequently, the appeal is dismissed. No order as to
costs.
(Rajesh Tandon, J.)
December 23, 2004
*Dhyani